V1.0 delivery roadmap

This is the execution roadmap for V1.0, with forecast dates from the July 13, 2026 plan. Dates are forecasts, not commitments. ROADMAP.md remains the implementation history and prior milestone record. P1 cuts cannot remove PDF comparison for active sources, Spanish V1 metadata, signing, retention, or deployment.

Phase 1 — prove the foundation (Jul 13–Sep 25, 2026)

Outcome Owner Dependencies Exit evidence
Active source registry human-verified Verification lead qualified reviewers, verification CLI all active sources named/dated; exceptions resolved
Verification/evidence schema and tests corrected Engineering registry authority decision required evidence reference, dated robots/terms/fetch-policy decision, shared watcher/publisher eligibility predicate, migration, and derived anti-fabrication tests pass
Public health distinguishes quiet/partial/failed/stale Engineering run model and schema status fixtures and staging output
Persistent production topology provisioned Operations + engineering host/storage decision runner, encrypted volume, scheduler, backup target, staging promotion receipt
V1 safety governance adopted Governance lead counsel/community panel reviewer policy, conflict policy, release authority
Architecture/data contracts frozen for RC Technical lead ADR and schema review accepted V1 boundary and migration plan

Risks: reviewer availability and machine-checked sources proving wrong. Mitigate with federal/high-use sources first and a parallel repair queue.

Phase 2 — close controls (Sep 14–Nov 13, 2026)

Outcome Owner Dependencies Exit evidence
Independent high-impact review and correction chain Engineering + governance reviewer policy, schema migration adversarial E2E tests and tabletop
Versioned status/release manifests and atomic publish Engineering hosting configuration reproducible staging release and rollback
Active PDFs yield safe passage comparison Engineering + verification retained bytes, extractor/manual workflow every active PDF passes extraction or reproducible manual-comparison rehearsal
Public/internal note boundary enforced Engineering + governance schema and copy policy legacy-note audit and publisher negative tests pass
Operable service Service owner alerts, backup target, runbooks fault injection and restore within RTO
Accessibility/security/legal review specialist owners release candidate surfaces reports with blocker/critical issues closed
Spanish V1 metadata reviewed Language + accessibility leads stable message catalog translator/independent review and stale-string fail-closed receipt

Risks: a quiet real-world period provides few alerts; use clearly labeled synthetic exercises. Never manufacture public change records. The accessible static review bundle and optional delivery helpers are the first cuts if critical-path evidence slips; active-PDF comparison is not cuttable while PDFs remain active.

Phase 3 — prove operations and release (Oct 19, 2026–Jan 29, 2027)

Freeze and receipt the complete operational baseline by October 16, then run eight consecutive eligible production-like cycles through December 14. Use the holiday contingency and January 4–15 RC window for clean migration, golden-corpus, security, accessibility, signing, deployment, restore, and rollback tests. A pre-baseline rehearsal or a sequence invalidated by a material control change does not count. Reconcile findings with requirements, close or explicitly block every P0, and hold the joint release review by January 29. Release only if every must-pass checklist item has evidence. Otherwise publish a dated hold decision and revised critical path.

Later options — post-V1

  • accessible static reviewer bundle and richer PDF/visual comparison beyond the bounded V1 path;
  • additional consumer integrations;
  • territories or new document classes only with governance/capacity review;
  • per-source adaptive outage thresholds from observed data;
  • independent nonprofit or fiscal-home governance;
  • daily cadence only if user evidence shows weekly latency causes harm and crawling remains responsible.

Milestones and decision gates

Gate Forecast Go condition Hold / kill condition
G1 verified foundation Sep 25, 2026 source/evidence schema, persistent runner, and attempt denominator proven source truth is ambiguous or deployment has no durable evidence store
G2b operational baseline Oct 16, 2026 all controls listed in the operations bootstrap-eligibility rule are installed, tested, and receipted before the Oct 19 cycle, including dated source-policy decisions, shared watcher/publisher eligibility enforcement, and replacement-or-gap disposition for all six planning-time active-but-unfetchable sources missing/unstable control, an unresolved active-but-unfetchable source, or material semantic change; rehearsal runs cannot count
G3 scope lock Nov 13, 2026 all P0 implemented/testable; no unresolved architecture blocker dual review/correction/public-copy boundary cannot be represented safely
G4 bootstrap close Dec 14, 2026 eight weekly receipts meet pre-V1 evidence rule falsely green status, evidence loss, or safety incident invalidates the sequence
G5 RC Jan 15, 2027 implementation complete; specialist blocker findings closed Sev-1/2 open or restore/signing/atomic publish fails
G6 V1.0 Jan 29, 2027 release checklist and operational outcomes pass source verification incomplete or a safety invariant fails

Outcome review cadence

Weekly delivery review covers requirement burn-up, verification, operations, risks, and explicit scope cuts. Governance reviews any harm signal immediately. At each gate, the owner records evidence and decision; schedule pressure is not evidence.