refund's permissionless-after-deadline path: economics, griefing, and sponsor control

Focused analysis for #30. refund (contracts/escrow/src/lib.rs) is the only state-changing function in the entire system callable by a completely arbitrary, unauthenticated caller once env.ledger().timestamp() >= escrow.deadline. No equivalent exists in milestones or maintenance-pool — both cancel_milestone and withdraw are admin-only with no timeout escape hatch (worth noting as a real inconsistency across the three contracts' sponsor-protection guarantees, discussed at the end).

Does calling refund on someone else's behalf cost the caller anything?

Yes. Whoever submits the transaction pays that transaction's Stellar resource fee (a small but non-zero, non-refundable cost). refund has no tip/reward mechanism — the caller gets nothing back for calling it; 100% of the escrowed amount goes to escrow.sponsor regardless of who submitted the transaction. So calling refund for a stranger is a strictly negative-EV action for the caller: real cost, zero benefit.

Is "anyone can call it" realistic, or does it implicitly assume mergefi-backend is the one calling?

Both, but for different reasons, and the honest answer requires separating "who realistically calls this in the common case" from "what is the fallback actually protecting against."

In the common case, the realistic caller is one of:

  • mergefi-backend itself. The README says it "likely does [call refund] for UX (so sponsors don't have to trigger it manually)" — the backend already holds signing keys and infrastructure to submit transactions for release/allocate/withdraw, so calling the permissionless refund path costs it nothing extra to automate.
  • The sponsor themselves. They have a direct economic incentive — it's their own money coming back — and can trigger it via the same wallet they used to call fund.

Neither of these needs refund to be permissionless — the backend could just as easily be given admin.require_auth() for this path too (it already has that for the pre-deadline case), and the sponsor could self-authorize like extend_deadline (added in this PR) does. Random altruistic third parties, with no relationship to the sponsor and no reward, are not a realistic source of calls — the negative-EV argument above means no rational disinterested party calls this. So in the day-to-day case, "anyone can call it" is not load-bearing at all; it's cosmetic relative to what actually happens on-chain.

The fallback is load-bearing, but only in the case it's designed for: backend unavailability. If mergefi-backend's operator ceases operating, loses its signing key, or is otherwise unable or unwilling to submit the refund transaction, the sponsor can still always call refund themselves once the deadline passes — this doesn't even need permissionlessness, since the sponsor could self-authorize. Where permissionlessness earns its keep is one level further: if the sponsor also can't or won't act (unresponsive, funds controlled by a multisig that's hard to coordinate quickly, sponsor is an organization that's since dissolved, etc.), a third party who has some other reason to care — e.g. the maintainer who was hoping to get paid and wants the issue reopened for a fresh bounty, a community member helping unwind a stalled sponsorship, or a future replacement service standing in for a defunct mergefi-backend — can still return the funds to the sponsor's address with no coordination or special permission needed. That's a genuine bankruptcy/custody-remoteness property: no single party's unavailability can permanently strand a sponsor's expired funds. It's a real guarantee, just one that matters in the tail case, not the median case.

Could a malicious "anyone" grief a sponsor by calling refund at the earliest possible moment?

No — not in the sense of causing the sponsor harm they didn't already agree to. Two things bound this:

  1. Funds always go to the address stored in the record (escrow.sponsor), never the caller. There is no parameter the caller controls that affects where money moves. So the only possible harm is timing, not redirection or theft.
  2. The deadline is the sponsor's own prior commitment. The sponsor chose deadline themselves at fund() time. Refund becoming callable-by-anyone at that exact moment is the contract keeping the promise the sponsor asked it to keep ("if this isn't resolved by time T, give my money back") — not a third party overriding the sponsor's preference. Calling it right at T is not materially different from the sponsor having set an alarm and calling it themselves at T; a third party doing it a few seconds earlier than the sponsor got around to it isn't a new harm, it's the same outcome arriving slightly sooner.

The real gap isn't griefing — it's that the sponsor has no way to change their mind after fund(). If a sponsor watches a PR get close to merging right as the deadline approaches and would rather wait a bit longer, the current contract gives them zero mechanism to express that — deadline is write-once. That's a legitimate design gap the issue asks to be resolved.

Design decision: sponsor-settable extension, not an admin/backend-controlled grace period

The issue asks whether to "implement a sponsor-settable auto-extend / grace-period flag... balancing against not undermining the sponsor-protective guarantee." Two shapes were considered:

  • Admin/backend-controlled grace period. Rejected. Letting the admin unilaterally delay refund's permissionless window would reintroduce exactly the dependency the permissionless design exists to remove — a sponsor's guaranteed recovery time would no longer be guaranteed if the backend (the same party whose unavailability is the scenario refund protects against) could also postpone it. Worse, it's a strict downgrade for sponsors trying to escape an unresponsive/compromised backend, which is the one scenario where permissionlessness matters most.

  • Sponsor-controlled, monotonic-only extension — implemented as extend_deadline in this PR. escrow.sponsor.require_auth(), callable only while status == Funded, and only accepted if new_deadline is strictly later than both the current stored deadline and the current ledger time (Error::InvalidDeadline otherwise). This directly answers the issue's question with a real mechanism: a sponsor who wants more runway can extend it themselves, at any point before the funds are paid out or refunded, including after the original deadline has already passed (re-closing a window that had opened, if nobody has claimed it yet). Because only the sponsor can call it and it can only push the deadline later, it can't be used by the admin/backend or any third party to trap funds against the sponsor's will, and it can't be used to retroactively undo a refund that already executed (blocked by the Funded-only status check, same as the existing early-refund admin path). This preserves the exact property that makes refund's permissionlessness valuable (nobody but the sponsor controls their own timeline) while closing the "sponsor has no say once deadline passes" gap the issue raises.

Cross-contract inconsistency (noted, not fixed here)

milestones::cancel_milestone and maintenance-pool::withdraw are both strictly admin-only with no timeout/escape-hatch concept at all — unlike escrow, a sponsor whose milestone or maintenance-pool admin goes permanently unresponsive has no path to recover undistributed funds except an off-chain intervention (e.g. a contract upgrade or manual backend action outside this system). This is a real asymmetry across the three contracts' sponsor-protection guarantees. It's out of scope for this PR (adding a deadline-based recovery concept to milestones/ maintenance-pool is a modeling change, not an access-control fix — pool deposits in particular have no natural single "deadline" the way a single-issue escrow does), but worth a dedicated design issue if the product wants parity. Not filed as a new issue here since it would need product input (what would "deadline" even mean for an open-ended, repeatedly-topped-up maintenance pool?) rather than a purely technical decision.